When your company applies the 'Owners English' or 'Specialty Contractors English' point-of-view dictionary, you'll see different tool names and term changes in the user interface. Learn how to apply the dictionary options.
This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials. These dictionaries are available in US English only. The default dictionary is designed for general contractors, which means that you will need to work with your Procore Administrator at your company and your Procore point of contact to access the other dictionary options.
General Contractors English (United States) - Default |
Owners English (Owner Terminology V2) |
Specialty Contractors English (Specialty Contractor Terminology) |
---|---|---|
Invoicing | Invoicing | Progress Billings |
Owner | Funding | Owner |
Owner/Client | Owner/Client | GC/Client |
Prime Contract Change Order | Funding Change Order | Client Contract Change Order |
Prime Contracts | Funding | Client Contracts |
Revenue | Funding | Revenue |
Subcontract | Contract | Subcontract |
Subcontractor | Contractor | Subcontractor |
Subcontractor Schedule of Values (SSOV) | Contractor Schedule of Values (CSOV) | Subcontractor Schedule of Values (SSOV) |
Mark one or more checkboxes to turn a prefill option ON when creating owner invoices in the Prime Contracts tool. These options allow Procore to automatically complete amounts on the owner invoice using data from eligible budget code line items on subcontractor invoices, direct costs, and commitment change orders in the approved statuses.
This table describes the prefill options for owner invoices.
Checkbox | Mark the checkbox to turn ON and... | Remove the checkbox to turn OFF... |
---|---|---|
Populate the Schedule of Values with Costs from the Selected Billing Period | Populate the line items in the schedule of values with eligible costs from corresponding budget codes on Approved subcontractor invoices, direct costs, and commitment change orders for the same billing period as the owner invoice. Notes:
|
Procore does NOT populate the schedule of values with costs. Users must manually enter the schedule of values data. |
Also Populate with Retainage from the Selected Billing Period | Only available when Populate the Schedule of Values with Costs from the Selected Billing Period is ON. Populates the the Work Retainage this Period ($), Materials Retainage ($), and Total Retainage Released ($) columns in the schedule of values with calculated retainage values from eligible subcontractor invoices in the Approved status. Note:
|
Procore does NOT populate the schedule with calculated retainage values from eligible subcontractor invoices in the Approved status. |
Include Backup from Direct Costs and Invoices in the Selected Billing Period | Populates the invoice's Attachments card with these sections: Uploaded Attachments, Attachments from Subcontractor Invoices, and Attachments from Direct Costs. It also:
|
Procore does NOT include an invoice backup. Instead, the invoice includes the Uploaded Attachments card to add attachments. |