When preparing an invoice in one of Procore's Project Financials tools, the 'Application for Payment' associated with the invoice shows the 'Current Amount Due' for the billing period. Procore calculates the value in Line '8. Current Payment Due' by subtracting the amount in Line 7. 'Less Previous Certificates for Payment' from Line 6. 'Total Earned Less Retainage.'
When viewing an upstream invoice for a client contract, funding, or prime contract, the invoice includes the 'Contractor's Application for Payment' shown below.
In the 'Contractor's Application for Payment' below, the 'Current Amount Due' is calculated as follows:
Line 6 minus Line 7 equals Line 8
$35,421.00 - $7,740.00 = $27,681.30
When viewing a downstream invoice for a commitment, the invoice includes a 'Summary Preview' that includes the 'Subcontractor's Application for Payment' shown below.
In the 'Subcontractor's Application for Payment' below, the 'Current Amount Due' is calculated as follows:
Line 6 minus Line 7 equals Line 8
$28,130.00 - $26,339.00 = $1,791.00