Why are my change order line items duplicated on my subcontractor invoice?

 Note
This answer is applicable only when a Commitment Change Order or a Commitment Potential Change Order is created before the first subcontractor invoice on the project and the Subcontractor SOV tab is disabled. See Enable or Disable the Subcontractor SOV Tab on a Commitment.

Answer

For ERP synced projects, when you create a line item for a commitment change order (or a commitment potential change order, if using a 2-tier change order setting), and the "Line Item" section of "New Line Item" is selected, Procore creates the following items:

comm.png

Since both the commitment's schedule of values and the change order's schedule of values are reflected on the subcontractor invoice, this line item appears twice on the subcontractor invoice:

re1.png

There currently is no functionality in Procore that can hide that $0 line item from the subcontractor invoice. When creating a subcontractor invoice, the $0 line item should be disregarded and only the change order line item should be billed against.  