Configure Overtime Rules for Timesheets
In Beta
This feature is currently in Beta.
Objective
To configure company and project level overtime rules in Company Timesheets.
Background
You can configure overtime rules to automatically apply overtime and double time rates. Company rules are applied to all projects by default and apply to Timesheets, Timecards, My Time, and Daily Log Timecard entries. You can create project rule sets that override the company rules, and apply them to specific projects.
Steps
Create Project Overtime Rules and Assign to Projects
- Navigate to the company's Timesheets tool.
- Click the Configure Settings
icon.
- Click Create New.
- Enter the name of the 'Project Rule Set'.
Note: Regular time is applied until employees exceed the thresholds you configure.
- Mark the checkbox to Apply Weekly Overtime Rules.
- Enter the number of hours in a week after which overtime is applied.
- Mark the checkbox to apply Daily Overtime Rules.
- Enter the number of hours in each day after which overtime time is applied.
- Mark the checkbox to apply Daily Double Time Rules.
- Enter the number of hours in each day after which double time is applied.
- Save the rule set:
- Click Save.
Note: You can assign the rule set to projects at a later time by clicking the link in the 'Assign projects' column.
- Click Save and Assign to Projects.
- Mark the checkboxes for the projects you want to assign the rule set to.
- Click Save.
Note
To edit what projects rule sets are assigned to, click the hyperlink in the 'Assigned Projects' column, select the projects, and click Save.