Objective

To approve or reject Prime Contract Change Order (PCCO) as the designated 'Reviewer.' 

Things to Consider

  • Required User Permission:
    • You must be the designated 'Reviewer' on the change order and your user account must have the following permissions:
      • 'Standard' permission or higher on the project's Change Orders tool
        AND
      • To view the PCCO in the Change Orders tool, 'Read-Only' or 'Standard' permissions or higher on the project's Prime Contracts tool and you must be designated as a member of the 'Private' list in the prime contract. 
  • Additional Information:
    • Only one (1) user can be designated as a reviewer on a PCCO.
    • A reviewer can only respond to a PCCO when it is in the 'Pending - In Review' or 'Pending - Revised' state.
    • PCCOs can only be reviewed in the Procore web application. Email responses from reviewers are NOT supported. 
 Notes

Steps

  1. If you are the designated 'Reviewer' on the PCCO, choose from these options:
    • Open the notification email about the PCCO was forwarded to your email Inbox. Look for the email with the subject line: 'FW: Prime Contract Change Order: PCCO #: Title.' See Forward a Change Order to a Project User by Email
    • In the Project Home page, locate the Prime Contract COs item in the My Open Items area. See About the Project Home Page.
    • Navigate to the project's Prime Contracts tool. Then locate the  in the Change Orders tab and click View. See View a Prime Contract
    • Navigate to the Change Orders tool. In the Prime Contracts tab, locate the change order and click View.
  2. Enter a response in the Reviewer's Response box. 
  3. Click Reject this PCCO or Approve this PCCO
    Note: The system sends an email notification about your response to the creator of the PCCO. 

    approve-this-pcco.png