Remove a Prime Potential Change Order or Change Order Request
Objective
To remove a Potential Change Order (PCO) or Change Order Request (COR).
Background
Before you can remove a Prime Contract Change Order (PCCO) from Procore (as described in Remove a Prime Contract Change Order (PCCO)), you must use the Steps below to remove any PCOs or CORs linked to that PCCO.
Things to Consider
- Required User Permission:
- 'Admin' on the project's Prime Contracts tool.
- Additional Information:
- Make sure that any change orders you want to remove are not added on any Invoices. If they are, those Invoices will need to be deleted in order to remove the change orders.
Steps
- Navigate to the project's Prime Contracts tool.
- Click the Change Orders tab.
This reveals these tables: Prime Contract Change Orders and Potential Change Orders. - Under Prime Contract Change Orders:
Notes:- You will need to locate the PCCO(s) in the 'Approved' Status that are also associated with the COR or PCO.
- If you have multiple PCCOs, you want to change the 'Approved' status to one of the unapproved statuses.
Important! For change orders, you must change the 'Approved' status in reverse approval order. For example, if the change orders were approved in (e.g., 1, 3, 4, 2, 5, 6), you must remove each approval in reverse order (e.g., 6, 5, 2, 4, 3, 1).
- Change the 'Approved' status on the PCCO(s) as follows:
- Next to the desired PCCO, click View.
This opens the change order in the Prime Contract tool. - Click Edit.
This places the change order into edit mode. - Select a status other than 'Approved' from the Status drop-down list.
- Click Save.
This changes the PCCO's status from 'Approved' to the status you selected.
- Next to the desired PCCO, click View.
- Under the Potential Change Orders Included in this PCCO area, unlink the COR or PCO as follows:
- Click View next to the desired COR or PCO.
This opens the COR or PCO. - Click Edit.
- Scroll to the Prime Contract Change Order drop-down list as shown below.
- Choose None.
- In the "Potential Change Orders" section, remove any existing linked potential change orders.
- Click Save.
- Click View next to the desired COR or PCO.
- Return to the Change Orders tab.
- The X next to the now unlinked change orders and potential change orders should now be red and clickable. Click the red X.
- Click on the OK on the pop-up to confirm that you want to remove the PCO or COR.