This page lists notable changes for the Project level Schedule tool in 2016. 

Added Milestone Filter To Schedules Tool (25/10/2016)

Updated the Project and Company-level Schedule tool to add a new 'Milestone' filter to the All, Day, Week and Month Views.

Now Turn Resource Names OFF In Schedule Tool (23/6/2016)

Updated the Schedule tool to create a configuration option in Configure Schedule Settings page which will allow users to turn OFF the display of resource names in tasks on the Week and Month calendar views.

Updated Schedule Tool Integrations (10/6/2016) 

Updated the Schedule tool so that the Related Items associated with a Schedule Task will now persist when a schedule is updated and imported through Procore Web. Related Items for a Schedule Task will be removed from a schedule when the task is deleted and the schedule is updated and imported through Procore Web.

Populated Start/Finish Variance For Imported MS Project Schedules (8/6/2016)

Updated Procore to ensure that the start and finish variance for a schedule are read when a Microsoft Project file (MPP) is imported to the Schedule tool via Procore Drive.

Users Can Now Upload Primavera P6 (XER) Schedules In Procore Web (20/5/2016)

Updated the project's Schedule tool to simplify the schedule upload process. Users with the appropriate permissions to the Schedule tool can now upload files in these formats: Microsoft Project (MPP), Microsoft Project Exchange, and SureTrack (MPX). Asta EasyPlan and Powerproject (PP), and Primavera Proprietary Exchange (XER). For details, see Upload a Project Schedule and Configure Advanced Settings: Project Schedule

Enhanced UI For Schedule Tool (15/4/2016)

Updated the Schedule tool to replace the existing 'MS Project 2010/13/16, Asta, Easyplan' drop-down list selection with a new selection that reads 'Microsoft Project, Asta PowerProject, Asta EasyPlan.' Also updated the labels on Configure Schedule Settings page as follows:

  • From "File Type" to "Schedule Data From"
  • From "MPP or MPX" to "Schedule File"
  • From "MPP file" to "Schedule File."

Also updated heading on the Procore Drive box to read "Schedule Integration." In addition, updated the text in the the Procore Drive box to read "Procore Drive can be used for schedule integration."

Users Can Now Integrate Asta Powerproject Schedules With Procore (24/2/2016) 

Users can now integrate Asta Powerproject schedules with Procore.  Procore updated the name of the selection option in the Upload Project Schedule Files drop-down list to give users the ability to upload Asta and Easyplan files. The selection option now reads: "MS Project 13/2010/16, Asta, Easyplan." See Integrate an Asta Powerproject Schedule