Objective

To upload a project schedule update that has first been revised in your third-party scheduling software.

Things to Consider

Steps

  1. Navigate to the project's Schedule tool.
  2. From the Gantt view, click + Upload Schedule
    Note: You are automatically redirected to the Update Schedule page in the tool's Configure Settings. 
  3. Select a schedule file from your computer. 
    • Click the Attach File link and select your schedule file. 
      OR
    • Drag the schedule file from your computer to the Drag and Drop File area.
  4. Navigate to the schedule file on your computer or network, then click Open
  5. Scroll to the bottom of the page and click Update.
    Note:
    • A "Schedule Uploaded, processing should start soon" message appears. Your schedule is placed into a job queue and the system updates the schedule on a task-by-task basis. Depending on the number of jobs in the queue and the size of your project schedule, the overwrite process may take some time to complete. You can continue working in Procore during this process 
    • To confirm that your upload is complete, click the links in the View By menu to view the schedule changes.
    • Important! While the schedule is being updated, it is recommended that you do not attempt to upload another schedule update. Doing so will add a second job to the queue and jobs will be processed in the order they were uploaded into the system. 