How are commitments numbered in Procore?
Answer
When you create a commitment (for example, a purchase order or subcontract) in Procore, the system automatically assigns it a commitment number by default. However, any user with access permission to create commitments can change the numbering scheme. Any change affects the current and subsequent commitment numbers.
- Using the Default Numbering Scheme on projects using the Procore Standard Cost Code List
By default, Procore's default numbering scheme identifies commitments using these abbreviations: Purchase Order (PO) and Subcontract (SC). If the Procore project has been assigned a project number, the number is also included after the abbreviation. The system then assigns numbers sequentially for each commitment type using a three-digit format. Examples showing how commitments are numbered by default are below:- PO-[Procore Project Number]-001, PO-[Procore Project Number]-002, and so on.
- SC-[Procore Project Number]-001, SC-[Procore Project Number]-002, and so on.
- Using the Default Numbering Scheme for ERP-Integrated Projects
By default, companies that have enabled the ERP Integrations tool use a similar numbering scheme. However, there are a few things to keep in mind, as detailed in the Important box below.Important
- When your cost code numbering scheme does NOT use the Procore Standard Cost Code list (for example, a Procore project integrated with Sage 300 CRE® might use the Sage 300 CRE® cost code list), the Procore project number is omitted.
- If your company has enabled the ERP Integrations tool, keep these best practices in mind:
- Ensure that your commitment numbering scheme does NOT exceed the maximum character limits of the integrated ERP system. See What is the maximum character length for a commitment's 'Number (#)'?
- Set up a customized numbering scheme when creating your first purchase order and first subcontract in Procore.
- Avoid renumbering your commitments after the two systems have initially synced.
- Avoid switching to a customized numbering scheme after the two systems have initially synced.
- Purchase Orders. PO-001, PO-002, and so on.
- Subcontracts. SC-001, SC-002, and so on.
-
Customizing the Numbering Scheme
Users can customize the numbering scheme at any time when creating a new commitment. Simply type over the default value in the Number (#) field with the format you want to use. After you click Create, all subsequent commitments will use your new numbering scheme.Tips
- If you decide to make a change to your project's commitment numbering scheme, remember to inform any teammates who may also be creating commitments in your project. This will ensure that the next commitment they create in the system is using the expected numbering scheme.
- If your company has enabled the ERP Integrations tool, keep these best practices in mind:
- Ensure that your commitment numbering scheme does NOT exceed the maximum character limits of the integrated ERP system. See What is the maximum character length for a commitment's 'Number (#)'?
- Set up a customized numbering scheme when creating your first purchase order and first subcontract in Procore.
- Avoid renumbering your commitments after the two systems have initially synced.
- Avoid switching to a customized numbering scheme after the two systems have initially synced.