Update the Percent Complete for a Schedule Task (Android)

Also available on  ios-gray-icon.jpg 

Objective

To update the Percent Complete field in the project's Schedule tool using an Android mobile device.

Things to Consider

Prerequisites 

Steps

  1. Navigate to the project's Schedule tool using an Android mobile device.
  2. Tap the schedule task you want to update.
  3. Tap Edit.
    edit-schedule-item-android.png
    Note: Percent Complete cannot be updated for Summary schedule tasks or Milestones.
  4. Enter the current Percent Complete for the task and tap Done.
    save-scheduled-item-android.png
    Note: You can enter a numeric value from 0 to 100. The value you enter must be a whole number. 
  5. Tap Save.
  6. The schedule task on the mobile device updates to show the amount you entered for Percent Complete.
    Note: These changes are also shown in the Schedule tool on the web application.
    schedule-item-percent-saved-android.png