Objective

To view resource assignments and requests over the course of a project using the project's labor graph.

Background

The labor graph provides a visual way to view assignments and requests over the duration of a project.

Things to Consider

Steps

  1. Navigate to the Company level Resource Planning tool.
  2. Click Project and select Projects List.
  3. Click the project name.
  4. Locate the 'Labor Graph'.
  5. Select to see Assignments, Requests, or Both.