Delete a Commitment Change Order

Objective

To delete a Commitment Change Order from the project's Commitments tool. 

Background

To remove a Commitment Change Order, you can click the red (x) icon on the line item. However, when the icon is grayed out and not available, it means the change order is associated with other items in Procore. The steps below show you how to remove associated items and then permanently delete a PCCO. 

 Important

Before you can perform a delete action, you must:

  •  Change the status of the change order from 'Approved' to another status as described below. If you want to change the status of multiple change orders, you must apply the status changes in reverse order from how they were approved. For example, if you approved the change orders in sequential order (001, 002, and 003), you will need to remove the 'Approved' status in reverse order (003, 002, 001). 
  • Unlink any Procore items associated with the change order. This may include Potential Change Orders (PCOs), Change Order Requests (CORs), and invoices as described in the Prerequisites below.

Things to Consider

Prerequisites

Steps

Navigate to the Change Orders Tab

  1. Navigate to the project's Commitments tool.
  2. Locate the commitment to work with. Then click its Number link. 
  3. Click the Change Orders tab. Depending on the number of change order tiers configured for the tool, the following tables appears in the tab:
    • Commitment Change Orders
    • Potential Change Orders
    • Change Order Requests

Change the Status of the Commitment Change Order from 'Approved'

  1. In the Commitment Change Orders table, locate the 'Approved' change orders.
  2. Click View to open the change order.
  3. Click Edit
  4. In the Status drop-down list, change the status from 'Approved' to a different status. 
  5. Click Save.

Delete the Commitment Change Order

  1. Click the Change Orders tab.
  2. In the Commitment Change Orders section, locate the change order to remove.
    delete-line-item5.png
  3. In the confirmation dialog box that appears, click OK to confirm the removal action for the selected change order.

See Also

 

If you would like to learn more about Procore's commitments software and how it can help your business, please visit our construction financials tool product page icon-external-link.png.