Create a Commitment Potential Change Order
Things to Consider
- Required User Permissions:
- Admin' level permissions on the project's Commitments tool.
Important
Do not use the steps below when:
- Additional Information:
- After a change order is approved, the next step depends on the Commitments tool's change order configuration setting:
- Limitations:
- To create a change order for a commitment, the commitment must be in the 'Approved' status.
- For companies using the
ERP Integrations tool: Show/Hide
- Additional considerations, requirements, and limitations can apply depending on the ERP system your account is integrated with. See Things to Know About your ERP Integration for details.
Steps
Create a Potential Change Order
- Navigate to the project's Commitments tool.
- Locate the commitment contract to work with. Then click its Number link.
- Click the Change Orders tab.
- Click Create Potential CO.

- Complete the following fields:
- Sign with DocuSign®
If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.
Tip
How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the
Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to
Log In to DocuSign®. Once you are signed in, you can prepare the DocuSign
® envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see
DocuSign®.
- Number
Accept the default number, enter a new number, or create a custom numbering scheme.
- Date Created
Shows the creation date and time. This value cannot be changed.
- Revision
Shows the revision number. The first version is zero (0), subsequent revisions are assigned in sequential order. A PCO might have several revisions, depending on its reviewer/approver feedback.
- Created By
Shows the Procore user who created the PCO. This value cannot be changed.
- Contract Company
Shows the name of the company responsible for performing the work on the contract.
- Contract
If you have been assigned access permissions to the Commitments tool, click this link to open the contract.
- Title
Enter a title for the PCO in this box.
- Status
Select the current state of the PCO. To learn more, see What are the default statuses for change orders in Procore?
- Commitment Change Order
Choose one (1) option button.
Note
This setting is only required when the Commitments tool is using the 3-Tier change order configuration setting. See What are the different change order tier settings in Project Financials?
- None. A PCO can be linked to a COR at a later time.
- Add to Existing. Link the PCO to an existing COR.
- Create New. Create a new COR. You also have the option to create a new change order at the same time.
- Change Reason
Select the reason for the PCO, either Client Request, Design Development, Allowance, Existing Condition, Back Charge, or any additional options created for your specific environment by your company's Procore Administrator. See Set the Default Change Management Configurations.
- Private
Mark this checkbox if you only want the PCO to be visible to users with 'Admin' permissions on the Commitments tool.
- Accounting Method
This field inherits the accounting method that was specified in the commitment contract. See How do I set the accounting method for a contract or funding?
- Description
Enter a more detailed description of the reason for the PCO.
- Request Received From
Select the Procore user for whom you are submitting the PCO.
- Schedule Impact
If known, provide an estimate for the additional number of days required to complete work when the PCO is approved.
In Beta
Note to users participating in the 'Subcontractor Estimated Completion' limited release beta program. When a user places a change order in the 'Approved' status and it includes a value in 'Schedule Impact' field of the change order, Procore automatically updates the 'Estimated Completion Date' field in the commitment contract by the number of days entered. To learn more about this program, see
Commitments: (Beta) Subcontractor Estimated Completion Date.
- Location
Use this drop-down list to select a location related to the PCO. You can select an existing location or Add a Multi-tiered Location to an Item.
- Reference
Add any other important tools, materials, drawings, or documents to use as a reference for the PCO.
- Field Change
Check this box if the PCO requires a field change.
- Paid in Full
Check this box to indicate you have received payment for this change.
- Attachments
Select and add any relevant documents.
- Click Create & Enter SOV.
Add a Schedule of Values to a Potential Change Order
When there are costs associated with a PCO, you must add line items to the SOV.
- In the Schedule of Values tab, click Add Line.
- For contracts using the Amount Based accounting method:
- Change Event Line Item
If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.
- Budget Code
Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS?
- Description
Enter a description for the line item. For example, type: Monthly Service Fee
- Amount
Enter the amount of the cost.
- Billed to Date
The system automatically calculates the amount billed on the commitment up to the current date.
- Amount Remaining
Enter the amount that has NOT been billed to the current date.
- Tax Code
Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?
- For contracts using the Unit/Quantity Based accounting method:
- Change Event Line Item
If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.
- Budget Code
Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS?
- Description
Enter a description for the line item. For example, type: Monthly Service Fee
- Qty
Enter the number of units.
- UOM
Enter the Unit of Measure (UOM).
- Unit Cost
Enter the Unit Cost in the box provided.
- Amount
The system automatically calculates the subtotal for you, based on the Qty, UOM, and Unit Cost entries.
- Click Save.
A GREEN banner appears to indicate that the Schedule of Values is saved.
Important
If you assigned a budget code that is not currently represented on your budget or if leave the budget code field blank, a confirmation message appears. To proceed, you must click OK to acknowledge the message. This action adds the corresponding line item(s) to your project's budget as non-budgeted line items.