Objective

To view see the Activity Feed of Lookahead schedules on the project's Schedule tool.

Things to Consider

  • Required User Permissions:
    • Read-only and above permissions on the project's Schedule tool with the 'View the Change History of a Lookahead' granular permission.

Steps

  1. Navigate to the project's Schedule tool.
  2. Click the Lookaheads tab.
  3. Click Activity Feed to show the change history of the entire Lookahead.