Set Up a Field Production Report
Objective
To set up a Field Production Report.
Background
This feature will help field teams understand the productivity of their workforce so they can catch problems early and make changes to maximize their profit. Field teams can track this information with a set of budgeted labour hours and budgeted production quantities that they have imported to Procore. They can then analyze the job’s productivity on a weekly or biweekly basis from the Field Production Report. This report provides teams with real-time insights into productivity rates so they can make more informed decisions on site.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Admin tool.
AND - 'Admin' level permissions on the project's Directory tool.
- 'Admin' level permissions on the project's Admin tool.