Update a Primavera P6 Schedule in Procore Drive
Objective
To update a project's schedule by uploading a revised Primavera P6 schedule file to Procore Drive.
Things to Consider
- Required User Permissions:
- 'Admin' level permission on the project's Schedule tool.
- Additional Information:
- In order to perform the steps below, you must have a computer running:
- A supported version of Microsoft Windows.
- Oracle’s Primavera P6 Professional Project Management software.
- Important! The schedule file cannot be updated in Procore. After modifying the schedule in Primavera, you can use the steps below to upload and apply the updated project schedule in Procore.
- In order to perform the steps below, you must have a computer running:
Prerequisites
- Integrate a Primavera P6 Schedule using Procore Drive
- The schedule file must be updated in Primavera.
Steps
- After updating the schedule file in Primavera, open Procore Drive on your computer.
- Select your company name and project from the drop-down menus.
- Click the Schedule tool.
Note: Make sure that the Schedule ID aligns with the Project ID of the file that you want to upload. - Click Export Schedule to upload the updated project schedule to your project in Procore. It will take a few minutes for your schedule to finish the upload process.
Note: If you would like Procore to automatically send a notification to members of your team when schedule updates are uploaded to the Schedule tool, mark the 'Upon Schedule Changes' option in the Configure Schedule Notification Emails.