Objective

To change your project's stage of construction to reflect its most current stage.

Background

Changing your stage of construction is important for your records and organization and it enables certain functions in Procore. 

Things to Consider

  • Required User Permissions:
    • 'Admin' on the project's Admin tool.
  • Additional Information:

Steps

  1. Navigate to the project's Admin tool.
  2. Under 'Project Settings' in the sidebar, click General.
  3. Under 'General Project Settings', select a stage from the Stage drop-down menu.
    Note: To create the selections in this list, see Add a Custom Project Stage.
    change-project-stage.png
  4. Click Update.