Change Events - FAQ Last updated Save as PDF Skip to main content Supportprocore.com Canada (English)América Latina (Español)Australia (English)Brasil (Português)Canada (English)Canada (Français)Deutschland (Deutsch)España (Español)France (Français)United Kingdom (English)United States (English)新加坡(简体中文)日本(日本語)ContactProcore App Login Search site Search Search Go back to previous article Sign in Expand/collapse global hierarchy Home Products Procore Web (app.procore.com) Procore User Guide Project Level Change Events Change Events - FAQ Expand/collapse global location Change Events - FAQ Last updated Save as PDF Can I create a change order for a Prime Contract before a downstream collaborator responds to an RFQ for a change event?Can I create a change order for a contract or funding before a downstream collaborator responds to an RFQ for a change event?Can I customize the numbering system for financial objects in Procore?Can I disable the Change Events tool?Can I enable the Change Events tool on my existing project?Can we set the cost basis for new CCOs 'Latest Cost' or 'Latest Price' in the Change Events tool?How are financial line items and budget codes updated across change objects?How can I troubleshoot an issue with the Procore Web Application?How do I track non-commitment costs on a change event?How do the Change Events tool's column display settings work?How does Procore calculate the Over/Under value in Change Events?Should I update my Budget View to add RFQ values to the budget?What are "related items" in Procore?What are 'production quantities'?What are Procore's default change types and change reasons?What are Procore's default cost codes?What are Procore's default cost types?What are configurable fieldsets and which Procore tools support them?What are custom fields and which Procore tools support them?What are custom sections and which Procore tools support them?What are the default 'Scope' options for change events in Procore?What are the default statuses for change events in Procore?What are the different RFQ statuses and how do they affect cost and change order amounts?What are the different change order tier settings in Project Financials?What is Procore's Recycle Bin?What is a budget code in Procore's WBS?What is a change event?What is a change order?What is a change order?What is a downstream collaborator?What is an upstream collaborator?What is the 'Budget ROM' column in Procore's Budget tool?What is the 'Budget ROM' column in Procore's Change Event tool?What values pull into a change order SOV from a change event?Which Microsoft Excel file versions can be attached to items in Procore?Which Procore tools can I use to add production quantities to my project's budget?Which Procore tools can I use to create a change event?Which Procore tools support Work Breakdown Structure?Which fields in the Budget tool can be configured as required, optional, or hidden?Which fields in the Change Events tool can be configured as required, optional, or hidden?Which filters can I apply to the Change Events tool?Which tools can I use to add production quantities to my project's budget?Which units of measure are included on Procore's master list?Which units of measure are included on Procore's master list?Why am I unable to assign users to a RFQ?
Change Events - FAQ Last updated Save as PDF Can I create a change order for a Prime Contract before a downstream collaborator responds to an RFQ for a change event?Can I create a change order for a contract or funding before a downstream collaborator responds to an RFQ for a change event?Can I customize the numbering system for financial objects in Procore?Can I disable the Change Events tool?Can I enable the Change Events tool on my existing project?Can we set the cost basis for new CCOs 'Latest Cost' or 'Latest Price' in the Change Events tool?How are financial line items and budget codes updated across change objects?How can I troubleshoot an issue with the Procore Web Application?How do I track non-commitment costs on a change event?How do the Change Events tool's column display settings work?How does Procore calculate the Over/Under value in Change Events?Should I update my Budget View to add RFQ values to the budget?What are "related items" in Procore?What are 'production quantities'?What are Procore's default change types and change reasons?What are Procore's default cost codes?What are Procore's default cost types?What are configurable fieldsets and which Procore tools support them?What are custom fields and which Procore tools support them?What are custom sections and which Procore tools support them?What are the default 'Scope' options for change events in Procore?What are the default statuses for change events in Procore?What are the different RFQ statuses and how do they affect cost and change order amounts?What are the different change order tier settings in Project Financials?What is Procore's Recycle Bin?What is a budget code in Procore's WBS?What is a change event?What is a change order?What is a change order?What is a downstream collaborator?What is an upstream collaborator?What is the 'Budget ROM' column in Procore's Budget tool?What is the 'Budget ROM' column in Procore's Change Event tool?What values pull into a change order SOV from a change event?Which Microsoft Excel file versions can be attached to items in Procore?Which Procore tools can I use to add production quantities to my project's budget?Which Procore tools can I use to create a change event?Which Procore tools support Work Breakdown Structure?Which fields in the Budget tool can be configured as required, optional, or hidden?Which fields in the Change Events tool can be configured as required, optional, or hidden?Which filters can I apply to the Change Events tool?Which tools can I use to add production quantities to my project's budget?Which units of measure are included on Procore's master list?Which units of measure are included on Procore's master list?Why am I unable to assign users to a RFQ?