Create Delay Entries

Also available on  ios-gray-icon.jpg  android-gray-icon.jpg

Objective

To create delay entries in the project's Daily Log tool.

Background

The Delays section allows you to track any delays that might occur or exist during the day. 

Things to Consider

  • Required User Permissions:
    • 'Standard' or 'Admin' level permissions on the project's Daily Log tool.
  • Additional Information:

Steps

  1. Navigate to the project's Daily Log tool.
  2. Scroll to the Delays section.
  3. Enter the following information:
    • Delay Type: Select the type of delay.
      Note: Delay type fields can be managed in the Daily Log's configure settings.
    • Start Time: Select the time the delay started using the hour and minute drop-down menus.
    • End Time: Select the time the delay ended using the hour and minute drop-down menus.
      Note: The Duration (Hours) field is calculated based on the Start Time and End Time entered. It will be entered automatically after saving your entry.
    • Location: Select a location from the Location drop-down menu. See Add Tiered Locations to a Project.
    • Comments: Enter any comments to further describe the entry.
    • Attachments: Attach any additional files to the entry. Drag and drop files from your computer to the Drag and Drop your File(s) area or click Upload Files to select files from your computer. 
  4. Click Create.