Objective
To enable Procore's financial markup capabilities on a prime contract.
Background
You can enable financial markup capabilities on individual prime contracts. This gives your project user's the ability to apply financial markup to PCCos associated with a commitment as described in Add Financial Markup to Prime Contract Change Orders.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Prime Contracts tool.
Steps
- Navigate to your project's Prime Contracts tool.
- Locate the contract to work with. Then click its Number link.
- In the contract, click the Advanced Settings tab.
- Click the Edit button.
- Under 'Financial Markup Settings', mark the Enable Financial Markup checkbox.
- Click Save.