Set Retainage for a Contract in Portfolio Financials

 Note
This information is intended for accounts with Portfolio Financials product in Procore. Please reach out to your Procore point of contact for more information. 

Objective

To enable and set retainage for a contract in Portfolio Financials.

Background

When retainage is enabled for a contract, retainage will automatically be calculated and displayed as invoices are submitted against schedule of values.

Things to Consider

  • Required User Permissions:
    • 'Limited' access to the project or higher.
      Note: Users with 'Limited' permissions can only set retainage when editing an existing contract they have access to.

Steps

  1. Navigate to the relevant Contract Room by clicking the name of the cost item in the project's Cost Tracker
    Note: Cost items with a Contract Room are marked with a ribbon icon-ribbon-pfcp.png icon.
  2. The Contract Room automatically opens to the Contract tab.
  3. Click the vertical ellipsis icon-ellipsis-vertical.png icon and select Edit
  4. Under Contract Overview, click the Retainage toggle to the ON icon-toggle-on-pfcp.png position.
    retainage-toggle.png
  5. Enter a retainage percentage. 
    Note: The percentage is set to 10% by default.
  6. Click Save