Create a Commitment Potential Change Order
Objective
To create a Potential Change Order (PCO) for a commitment and complete its Schedule of Values (SOV).
Background
When a change to the scope of work or the original commitment contract amount occurs during a construction project, the change management process begins. You can create a PCO if your company's Procore Administrator configures the Commitments tool with the two (2)- or three (3)-tier change order configuration setting. See What are the different change order tier settings in Project Financials?
Things to Consider
- Required User Permissions:
- Admin' level permissions on the project's Commitments tool.
Important
Do not use the steps below when:- The Change Events tool is enabled on the projects. Follow these steps instead: Create a Commitment Potential Change Order from a Change Event.
- The Commitments tool is configured with the one (1) tier change order configuration setting. Follow these steps instead: Create a Commitment Change Order.
- Admin' level permissions on the project's Commitments tool.
- Additional Information:
- After a change order is approved, the next step depends on the Commitments tool's change order configuration setting:
- For the two (2)-tier change order setting, continue with Create a Commitment Change Order.
- For the three (3)-tier change order setting, continue with these steps: Create a Change Order Request for a Commitment
- After a change order is approved, the next step depends on the Commitments tool's change order configuration setting:
- Limitations:
- To create a change order for a commitment, the commitment must be in the 'Approved' status.
- For companies using the ERP Integrations tool: Show/Hide
- Additional considerations, requirements, and limitations can apply depending on the ERP system your account is integrated with. See Things to Know About your ERP Integration for details.
- Additional considerations, requirements, and limitations can apply depending on the ERP system your account is integrated with. See Things to Know About your ERP Integration for details.
Prerequisites
- The Commitments tool must be configured with the two (2) or three (3) tier change order configuration setting. See What are the different change order tier settings in Project Financials?
Steps
Create a Potential Change Order
- Navigate to the project's Commitments tool.
- Locate the commitment contract to work with. Then click its Number link.
- Click the Change Orders tab.
- Click Create Potential CO.
- Complete the following fields:
- Sign with DocuSign®
If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark. - Number
Accept the default number, enter a new number, or create a custom numbering scheme.Tip
How are numbers assigned? To learn how Procore assigns numbers and to understand your custom numbering options, see Can I customize the numbering system for financial objects in Procore? - Date Created
Shows the creation date and time. This value cannot be changed. - Revision
Shows the revision number. The first version is zero (0), subsequent revisions are assigned in sequential order. A PCO might have several revisions, depending on its reviewer/approver feedback. - Created By
Shows the Procore user who created the PCO. This value cannot be changed. - Contract Company
Shows the name of the company responsible for performing the work on the contract. - Contract
If you have been assigned access permissions to the Commitments tool, click this link to open the contract. - Title
Enter a title for the PCO in this box. - Status
Select the current state of the PCO. To learn more, see What are the default statuses for change orders in Procore? - Commitment Change Order
Choose one (1) option button.Note
This setting is only required when the Commitments tool is using the 3-Tier change order configuration setting. See What are the different change order tier settings in Project Financials?
- None. A PCO can be linked to a COR at a later time.
- Add to Existing. Link the PCO to an existing COR.
- Create New. Create a new COR. You also have the option to create a new change order at the same time.
- Change Reason
Select the reason for the PCO, either Client Request, Design Development, Allowance, Existing Condition, Back Charge, or any additional options created for your specific environment by your company's Procore Administrator. See Set the Default Change Management Configurations. - Private
Mark this checkbox if you only want the PCO to be visible to users with 'Admin' permissions on the Commitments tool. - Accounting Method
This field inherits the accounting method that was specified in the commitment contract. See How do I set the accounting method for a contract or funding? - Description
Enter a more detailed description of the reason for the PCO. - Request Received From
Select the Procore user for whom you are submitting the PCO. - Schedule Impact
If known, provide an estimate for the additional number of days required to complete work when the PCO is approved. - Location
Use this drop-down list to select a location related to the PCO. You can select an existing location or Add a Multi-tiered Location to an Item. - Reference
Add any other important tools, materials, drawings, or documents to use as a reference for the PCO. - Field Change
Check this box if the PCO requires a field change. - Paid in Full
Check this box to indicate you have received payment for this change. - Attachments
Select and add any relevant documents.
- Sign with DocuSign®
- Click Create & Enter SOV.
Add a Schedule of Values to a Potential Change Order
When there are costs associated with a PCO, you must add line items to the SOV.
- In the Schedule of Values tab, click Add Line.
Notes
- If sub-jobs are enabled (see Enable Sub Jobs on Projects for WBS), the Sub Jobs drop-down list contains all sub-jobs added to the project. See Add 'Sub Job' Segment Items to a Procore Project.
- All cost codes related to the sub-jobs will appear in the following field.
- For contracts using the Amount Based accounting method:
- Change Event Line Item
If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event. - Budget Code
Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS? - Description
Enter a description for the line item. For example, type: Monthly Service Fee - Amount
Enter the amount of the cost. - Billed to Date
The system automatically calculates the amount billed on the commitment up to the current date. - Amount Remaining
Enter the amount that has NOT been billed to the current date. - Tax Code
Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?
- Change Event Line Item
- For contracts using the Unit/Quantity Based accounting method:
- Change Event Line Item
If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event. - Budget Code
Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS? - Description
Enter a description for the line item. For example, type: Monthly Service Fee - Qty
Enter the number of units. - UOM
Enter the Unit of Measure (UOM).Notes
- To view the default options in the list, see Which units of measure are included on Procore's master list?
- To update the available options in the list, see Update a Unit of Measure to the Unit of Measure Master List.
- Unit Cost
Enter the Unit Cost in the box provided. - Amount
The system automatically calculates the subtotal for you, based on the Qty, UOM, and Unit Cost entries.
- Change Event Line Item
- Click Save.
A GREEN banner appears to indicate that the Schedule of Values is saved.Important
If you assigned a budget code that is not currently represented on your budget or if leave the budget code field blank, a confirmation message appears. To proceed, you must click OK to acknowledge the message. This action adds the corresponding line item(s) to your project's budget as non-budgeted line items.