Objective

To describe the different ways you can update the line items on a contract's Schedule of Values (SOV).

Background

After creating a contract, you can choose from three (3) methods to update line items to your contract's SOV: 

  • Add Line Items to the SOV
    If your contract's SOV only has a few line items or if you want to manually add new line items to the SOV, use the 'Add Line' button to manually enter each SOV line item. 
  • Create the SOV from the Project's Budget
    If your want to structure your contract's SOV to match your budget line items, Procore gives you an option to import your SOV line items directly from the Procore's Budget tool. This method automatically creates the contract's SOV for you using your project's budget line items as its data source. 
  • Import the SOV from a CSV File
    If you would prefer to build your contract's SOV using a spreadsheet program, such as Microsoft Excel, you can download a blank template that matches your contract's table structure, add your SOV line items to the spreadsheet, save the file to the Comma Separated Values (CSV) file format, and then import your line items. You can also use the import process to replace all existing line items on your contract's SOV or you can keep any existing line items and add additional ones. 

Things to Consider

Prerequisites

Steps

There are several ways to add and update line items on a contract's SOV:

Add Line Items to the SOV

  1. Navigate to the project's Prime Contracts tool.
  2. Locate the contract to update and click its Number link. 
  3. Click the Schedule of Values tab.
  4. Click Add Line.
  5. Complete the data entry as follows:
    1. Budget Code
      Select a budget code or click Create Budget Code. See What is a budget code in Procore's WBS? 
    2. Description
      Enter a description for the line item. For example, type: Monthly Service Fee
    3. Qty
      Enter the number of units.
    4. UOM
      Select a Unit of Measure (UOM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a Unit of Measure to the Unit of Measure Master List.
    5. Unit Cost
      Enter the cost per unit in this box. You'll notice that the value in this column contains four (4) decimal points (for example, $0.0000) to allow you to enter the specific value required to calculate accurate pricing. 
      Example
      If you are buying 50,000 units for $1,006,625.00, you would enter a unit price of $20.1325. 
    6. Amount
      The system automatically calculates the subtotal for you, based on the QtyUOM, and Unit Cost entries. 
  6. Repeat the above steps for all line items.
     Tip
    Want to arrange the line items on your schedule of values into groups? Click the Add Group menu and select the desired grouping options. The default options include Cost Code, Cost Type, Sub Job (if enabled), as well as any custom segments that have been added for your company or project. See What are Segments and Segment Items
  7. Choose one of these options:
    • Click Save
      OR
    • Click Save & Email.  

Create the SOV from the Project's Budget

 Note

If you will be creating the contract SOV from the project's budget as described below, ensure your contract's SOV is blank. You can only use these steps below when the SOV has zero (0) line items. You must also:

  1. Navigate to the project's Prime Contracts tool. 
  2. Locate the contract to update. Then click its Number link.
  3. Click the Schedule of Values tab.
  4. ​Below the 'Schedule of Values' table, click Import. Then choose SOV from Budget from the drop-down menu.

    import-sov-from-budget.png
     
  5. In the 'Import Schedule of Values from Budget?' window, click Import
    • If the SOV is blank, the following message appears. 

      import-sov-blank.png
    • If the SOV has existing line items, all existing line items will be replaced with the line items in the budget.
      import-sov-from-budget-window.png

      Procore replaces any existing line items on the Schedule of Values with the line items current in the project's budget. This can take several minutes. Once the import is complete, a GREEN banner appears to indicate the action was successful and the line items appear in the 'Schedule of Values' table. 

Import the SOV from a CSV File

  • Download a CSV Template
  • Add Line Items to a CSV Template
  • Import the Completed CSV Template to Procore

Download a CSV Template

  1. Navigate to the Prime Contracts tool. 
  2. In the table, click a Number link to open the contract.
  3. Under the General tab, click Schedule of Values.
  4. In the Schedule of Values card, click Edit. 
    This places the SOV into edit mode
  5. Below the table, click Import and choose SOV from CSV.
    This opens the Import Schedule of Values from CSV window. 

    prime-import-sov-from-csv.png
     
  6. Expand Customize CSV Delimiter.
  7. Choose a delimiter for the template file: Comma or Semicolon.
    The system's default option is Comma
  8. Click Download CSV Template and choose: Blank Template or Template with Existing Line Items
    The downloads the selected template to your web browser's configured location. 

Add Line Items to a CSV Template

  1. Open the downloaded template in a spreadsheet editor.
  2. Enter the line item data using the appropriate accounting method for the prime contract. See How do I set the accounting method for a contract or funding?

Import the Completed CSV Template to Procore

  1. Navigate to the Prime Contracts tool. 
  2. In the table, click a Number link to open the contract.
  3. Under the General tab, click Schedule of Values.
  4. In the Schedule of Values card, click Edit
    This places the SOV into edit mode.
  5. Below the table, click Import and choose SOV from CSV.
    This opens the Import Schedule of Values from CSV window. 

    prime-import-sov-from-csv.png
  6. Upload the file as follows:
    • Click Upload File and select the completed template to upload.
      OR
    • Drag-and-drop the completed template to the CSV File area.
  7. Depending on the state of your prime contract, choose the appropriate option:
    • To add more line items to the prime contract, select Add Additional Line Items, then click Import
    • To replace all existing line items on the prime contract with the template, select Replace Existing Line Items, then click Import.

Procore imports the template and displays a success banner. If you see an error message, click Show Error to learn why the import failed.