Create a Subcontract (Legacy)
Legacy Content
This tutorial details Procore's legacy experience for creating a subcontract. The information on this page will be replaced with updated content when the redesigned commitments beta experience is generally available. To learn about this release and its timeline, see Project Financials: Modernized Experience for Commitments.
Important! If you are using the commitments beta experience, please see the Create Subcontracts tutorial instead of the information below.
Objective
To create a subcontract in Procore using the project's Commitments tool.
Background
Subcontracts can be awarded during both the preconstruction and construction phases of a project and are typically created and tracked in Procore by project management. After a prime contract award, the project manager creates purchase orders and subcontracts for specific trades to secure materials and subcontractor services for a project.
Things to Consider
- Required User Permissions:
- To create a subcontract and see/enter data on the Schedule of Values (SOV) tab:
- 'Admin' level permissions on the project's Commitments tool.
OR - 'Standard' level permissions on the project's Commitments tool and the 'Allow Users to See SOV Items' setting must be enabled and your name must be selected in the 'Select a Person' drop-down list
- 'Admin' level permissions on the project's Commitments tool.
- To create a subcontract only, 'Read Only' or 'Standard' level permissions on the project's Commitments tool with the 'Create Work Order Contract' granular permission enabled on your permissions template.
- To create a subcontract and see/enter data on the Schedule of Values (SOV) tab:
- Additional Information:
- An alternative way to create a subcontract is to award a winning bid and convert it into a subcontract. See Award a Winning Bid and Convert it into a Subcontract.
- To set the accounting method for the subcontract, see How do I set the accounting method for a contract or funding?
- After creating a subcontract, you have these options for creating change orders:
- If your subcontract is configured for 1-Tier Change Orders. Continue with Create a Commitment Change Order.
- If your subcontract is configured for 2-Tier Change Orders. Ensure the subcontract is in the 'Approved' status and continue with Create a Commitment Potential Change Order from a Change Event.
- If your subcontract is configured for 3-Tier Change Orders. Ensure the subcontract is in the 'Approved' status and continue with Create a Commitment Potential Change Order from a Change Event.
Prerequisites
- Configure Advanced Settings: Commitments
- To use the Procore + DocuSign® integration to request signatures on a contract, see Enable or Disable the DocuSign® Integration on a Procore Project.
Steps
Step 1: Create a Subcontract
- Navigate to the project's Commitments tool.
- Click +Create and select Subcontract from the drop-down menu.
- In the 'General' tab under 'General Information', do the following:
- Sign with DocuSign®
If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark. - Number #
Accept the default number, enter a new number, or create a custom numbering scheme.Tip
How are numbers assigned? To learn how Procore assigns numbers and to understand your custom numbering options, see Can I customize the numbering system for financial objects in Procore? - Title
Enter a descriptive title for the subcontract.Notes
- If your company has enabled the ERP Integrations tool, be aware that some integrated ERP systems impose character limits on the 'Title' field when data exported from Procore is imported into their system.
- For details about character limits, see What is the maximum character length for a commitment's 'Title'?
- Contract Company
Select the company responsible for completing the work on the subcontract (for example, American Construction Co.).
Notes:- To appear in this list as a selection, add the company to the Project Directory. For details, see Add a Company to the Project Directory or Import Users & Vendors into your Project Level Directory Tool (Procore Imports).
- You must select a contract company before you can name an invoice contact.
- Invoice Contacts
Select one (1) or more employees of the 'Contract Company' to designate as the invoice contact(s). After saving the subcontract, any users added here will be added to the 'Private' list. You must select a 'Contract Company' before you can select invoice contacts. - Status
Assign a status to the subcontract. To learn about the available statuses and which commitment statuses reflect contract amounts in your project's budget, see What are the default commitment statuses in Procore? - Executed. Mark this checkbox to denote that the subcontract was fully signed and executed.
Notes
- Many Procore users choose to place a checkmark in the Executed box when placing the commitment into the 'Approved' or 'Complete' status.
- The time at which your project team places a checkmark in the Executed box should always be aligned with your project's unique business process
- Private
Mark the checkboxes and choose any project users or collaborators from the 'Select a Person' list. To learn more about the privacy options, see Change the Privacy Settings for a Commitment.- Make this visible to only administrators and the following users
Mark this checkbox to limit the visibility of the purchase order to users with 'Admin' on the project's Commitments tool and users specified in the 'Select a Person' drop-down list. - Allow these users to see SOV items
Mark this checkbox in this box to limit the visibility of the Schedule of Values (SOV) items on the purchase order to users with 'Admin' on the project's Commitments tool and users specified in the 'Select a Person' drop-down list.
- Make this visible to only administrators and the following users
- Default Retainage
Specify the percentage amount of retainage to withhold on the first subcontractor invoice. For example, it is a common practice to enter 5 or 10% in this field.Notes
- The 'Default Retainage' amount set on the subcontract will only affect the amount on the first subcontractor invoice.
- Editing this value after creating the first subcontractor invoice will NOT affect the retainage amount on subsequent invoices.
- In order to set or release the retainage amount on a subsequent invoice, complete the steps in Enable Retainage on a Commitment. Next, use one of these Procore tools to set or release retainage on that invoice:
- Commitments. Set or Release Retainage on a Subcontractor Invoice.
- Invoicing. Set or Release Retainage on a Subcontractor Invoice.
- If you would like to set up retention rules that automatically adjust withheld amounts on your subcontractor invoices, see Enable Sliding Scale Retention Rules on a Commitment's Invoices.
- Description
Provide additional information, as necessary. - Attachments. Attach any related materials such as pricing quotes, receipts, signed purchase orders, and so on. You may attach files that have been uploaded to your project or drag and drop files from your local computer.
- Sign with DocuSign®
- Scroll to the Contract Dates section and enter the following:
- Start Date. Select the date when the scope of work will begin on the job site.
- Estimated Completion Date. Select the estimated date of when the scope of work will be finished.
- Signed Contract Received Date. Select the date when the subcontract was officially signed.
- Actual Completion Date. Select the date when the scope of work was deemed complete.
- Scroll to the Additional Information section and enter the following:
- Inclusions. Disclose any inclusions that may not be clearly stated in the related contract documents.
- Exclusions. Disclose any exclusions that may not be clearly stated in the related contract documents.
- Click one (1) of these buttons:
- Create. Click this button to save the new subcontract and return to the 'General' tab in view mode.
- Create & Enter SOV. Click this button to save the new subcontract and jump to the 'Schedule of Values' tab in edit mode. Continue by entering the SOV.
- Complete with DocuSign®. Click this button to complete the subcontract with the DocuSign® integration. See Complete a Commitment Contract with DocuSign®.
Step 2: Enter the Schedule of Values (SOV)
There are two ways to enter the Schedule of Values (SOV) on a subcontract:
Add Line Items to the SOV
Notes
- If your company is using the Procore + Integration by Ryvit integration and your Integration by Ryvit system is configured to use the Calculated Method, Integration by Ryvit will NOT allow the use of Lump Sum (LS) as a unit of measurement.
- If you are using the 'Override Subtotal', you must ONLY input the Subtotal Amount. The Integration by Ryvit integration will then create an 'LS' item in Integration by Ryvit.